The 38th span of the 6.15-kilometre long Padma Bridge will be installed at Mawa point in Louhoganj on Saturday.
The span will be installed on first and the second pillars at the Mawa-end in Munshiganj.
Following the installation of the 38th span, the 5,750 meters or over 5.75 kilometers of the bridge will become visible.
On November 12, the 37th span of the bridge was installed, bringing a total of over 5.55km of the huge structure into view.
Meanwhile, after the installation of the 38th span, the 39th span (2-D) will be installed on the Piers 10 and 11 on November 23, the 40th span (2-E) on the Piers 11 and 12 on December 2, and the 41st span (2-F) on the Piers 12 and 13 on December 10.
The 6.15-km long double-layered bridge will have a total of 41 spans which would be installed on 42 piers — 21 piers at Mawa-end and other 21 piers at Jajira-end as all the piers have already become visible.
The multi-purpose Padma Bridge is expected to be opened in 2021.
News Desk :: Students from Dhaka College and City College once again clashed in the capital’s Science Lab area on
News Desk :: TIn southern Morocco, volunteers are hunting for waste embedded in the sand, and they don’t have to
News Desk :: The third round of talks between the BNP delegation and the National Consensus Commission is currently taking
News Desk :: Bangladesh Ambassador to Qatar Md Nazrul Islam received Prof Yunus upon his arrival at Hamad International Airport
News Desk ::In yet another price hike within just two days, the Bangladesh Jewellers Association (BAJUS) has announced a new
He claims that false and conspiratorial propaganda is being carried out against Rahima Khanam, a UK expatriate daughter of Maulana
News Desk :: The suspect, identified as Mozammel Hossain, a CNG-run autorickshaw driver from Gorai-Sakhipur road, is the son of
News Desk :: In a major policy shift, Russia’s Supreme Court on Thursday officially removed the Taliban from its list